Completed Projects in YEMEN |
||||
Item No. | Description | Client | Consultant | |
1 | Topographic Survey ,Soil Investigation, Foundation and Civil Construction for Power Supply to Local Area -Lot (2B-1) for 132kV Substation in Suq Abs and Bajil Hajia Governorate | Public Electricity Corporation ,Ministry of Electricity
EPC Contractor: CHINT Electric Company Ltd |
Kuljian Corporation | Jan to Oct 2013 |
2 | Topographic Survey ,Soil Investigation, Foundation and Civil Construction for Design ,Supply and installation of HV OHL, HV/MV and MV/LV substations package II :Dhamar Area (Sana’s ,Dhamar and IBB Governments Lot(2) Dhamar Substation & Lot(3) Yarim Substation ) | Public Electricity Corporation ,Ministry of Electricity
EPC Contractor: CHINT Electric Company Ltd |
Kuljian Corporation | 2014-2015 |
3 | One Deep Water Drilling Project for United Arab Emirate (UAE) Embassy-Sana’a
Depth: 950m |
United Arab Emirate (UAE) Embassy-Sana’a
|
May to Sep 2011 | |
4 | Civil Construction and Maintenance of Embassy Building | Chinese Embassy- Sana’a | Sep 2008 to Dec 2009 | |
5 | One Deep Water Drilling Project for Chinese Embassy-Sana’a
Depth: 1000m |
Chinese Embassy- Sana’a | Jan to May 2011 | |
6 |
One Deep Water Drilling Project for Chinese Embassy-Sana’a Depth: 450m |
Chinese Embassy- Sana’a | 2005 | |
7 |
Topographic Survey, Soil Investigation, and Piling Foundation Construction for Al- Hiswa 1 x 60 MW Thermal Power Station Project in Aden
|
Funded By Chinese Government | CMEC | 2004-2005 |
8 |
Soil Investigation and Topographical Survey for Foreign Affair Ministry’s office Building in Sana’a
|
Yemen Foreign Ministry
Funded By Chinese Government |
2005 | |
9 |
Soil Investigation and Topographical Survey for Sana’a Military Hospital
|
Funded By Chinese Government | 2009 | |
10 | Cement Raw Materials Investigation, Soil Investigation and Topographical Survey for AYCC Arabian Yemeni Cement Plant, Mukalla
|
Saudi Investor & EPC Contractor: SINOMA International
5000 T/D |
HOLTIEC Consulting Private Limited, India | 2006 |
11 | Cement Raw Materials Investigation, Soil Investigation and
Topographic Survey for Yemen AAA Abyan Cement Plant near Aden and Deep Water Well Drilling |
Saudi Investor & EPC Contractor: CNBM, China
5000 T/D |
Cement Consultancy
Associates Limited, Britain |
2007 |
12 | Cement Raw Materials Investigation, Soil Investigation and
Topographic Survey for Yemen YSCC Cement Plant in Abyan |
Saudi Investor & EPC Contractor: SINOMA – CDI
5000 T/D |
HOLTIEC Consulting Private Limited, India | 2007 |
13 | Cement Raw Materials Investigation, Soil Investigation, Topographic Survey and Water Supplies System Construction for HODEIDAH Bajel Cement Plant Extension Project | Yemen National Cement Company & General Contractor: CMEC ; 1000 T/D
Funded By Chinese Government |
Cement Consultancy Associates Limited, Britain | 2010 |
14 | Topographic Survey and Soil Investigation for Yemen National Library, Sana’a | Funded By Chinese Government | May to July 2008 | |
15 | Soil Investigation and Civil Work Construction of Container’s Scanner System for Yemeni Seaports and Border (Aden, Mukalla, Hodeidah, Shihan & Harad) | Yemen Customs Authority & NUCTECH Company Limited
Funded By Chinese Government |
COTECNA Inspection S.A., Switzerland | January 2007 to
December 2008 |
16 | Civil Construction Project of Packages BL1 and BL2 for YEMEN LNG Plant in BalHaf, Yemen;
Contract No.: YE-001-37-PCC-CNT-54009 |
SKEC – SAMWHAN & TOTAL
Yemen Yemen LNG Company |
2006 to 2007 | |
17 | Wadi Hadhramout Agriculture Development Project Phase 3 Addendum contract for supplementary studies – Geology and Hydrogeology Drilling and Development of two deep wells.
Funded by: Arab Economic & Social Dev. Fund. |
Ministry of Agriculture, Yemen | British Coode Blizard Co. | 1997 |
18 | Wadi Hadhramout Agriculture Development Project Phase II Contract No.1 – Drilling and development of 60 boreholes Funded by: World Bank and Arab Economic and Social Development Fund. | Ministry of Agricultural, South Yemen | Sir M. MacDonald & Partner Limited, Britain | 1984 – 1987 |
19 | Greater Aden Water Supply Project Second Stage
Contract No.1 – Drilling and Development of 30 Boreholes. Funded by: World Bank |
National Water and Sanitation Authority Aden Branch | DHV Consultants, Netherlands | 1989 – 1991 |
20 | Al-MUKALLA Water Supply Project first stage Contract No.2 – Drilling & Testing of 17 boreholes
Funded by: World Bank |
National Water & Sanitation Authority MUKALLA Branch | Egyptian Consultants Group | 1990 – 1993 |
21 | Groundwater Investigation, Geophysical Survey and Test Wells in Hadhramout, SHABWAH and MAHARA Governorate First Phase(PDY/87/007)
Funded by: International Development Associate(IDA) |
UNDP Sana’a office | Dar Al-Handasah Consultants | 1991 – 1993 |
22 | Tarim Regional Water Supply Project
Contract No. 1 – Drilling, Equipment and Testing of 8 boreholes. Funded by: World Bank |
National Authority Water & Sanitation | Dar Al-Handasah Consultants | 1995 – 1998 |
23 | Sana’a Water Supply Project
Contract No: SWSSP-7 – Drilling & Testing of 15 deep water wells Funded by: World Bank |
National Water & Sanitation Authority Sana’a Branch | Dar Al-Handasah Consultants | 2000 – 2003 |
24 | MUKALLA Water Supply and Sanitation Project Contract No: MUKCW-1
Drilling, Rehabilitation and Replacement of Wells, Geophysical Survey for Groundwater Investigation and Well Drilling. Funded by: World Bank |
Local Corporation for Water supply and Sanitation – Coastal Area, Hadhramout, Ministry of Water & Environment | British MWHJ | September 2005
to January 2009 |
25 | Drilling of Exploratory Wells for Hydro-Geological Investigation in IBB Contract No: IBBCW-1
Funded by: World Bank |
Local Water and Sanitation Corporation IBB Branch | Dar Al-andasah Consultants | 2008 to 2009 |
26 | Soil Investigation and Pile Foundation Construction
for Aden governor office building in Aden |
Funded by Chinese Government | 1985 | |
27 | Soil Investigation and Foundation Construction Project for LAHEJ Hospital | Funded by Kuwait Government | 1986 | |
28 | Soil investigation and pile foundation construction for
Chinese Embassy office building in Aden |
Funded by Chinese Government | 1988 | |
29 | Soil Investigation and Topographical Survey for Aden Ring Road Project | Funded by Chinese Government | 1988 | |
30 | Soil investigation and pile foundation construction for Aden Gymnasium in 1989 | Funded by Chinese Government | 1989 | |
31 | Topographical Survey, Soil Investigation and Water Well drilling for Aden – MUKALLA Road Project | Funded by Chinese Government | 1975-1979 | |
32 | Topographical Survey, Soil Investigation and Water Well drilling for HUDEIDAH – Sana’a Road Project | Funded by Chinese Government | 1966-1968 | |
33 | Aden Water Supply System Designing & Construction | Funded by Chinese Government | 1971-1973 | |
34 | Sana’a Water Supply System Designing & Construction | Funded by Chinese Government | 1968-1970 |